PWD006-11-02 Udumbanchola

Improvement to Ramakkalmedu - Cumbummedu Vannapuram Road- Part 1- Cumbummedu To Njondical- 28.1km- Work Contract

Estimated amount

₹99.82 crore

₹99,82,11,663 · ₹80.62 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Ramakkalmedu-CVannapuram Road

Completed
99%Physical progress
101.4%Financial progress
Scheduled start25-02-2023
Scheduled completion24-09-2025
Implementing agency (SPV)
KRFB
Contract amount
₹97,09,19,643₹97.09 crore
Amount paid
₹90,91,24,498₹90.91 crore
Paid to contractor
₹78,84,49,269₹78.84 crore
Administrative sanction (AS)
₹30,00,00,000₹30 crore
Financial sanction (FS)
₹99,82,11,663₹99.82 crore
Technical sanction (TS)
₹97,12,29,392₹97.12 crore
Tender amount
₹74,89,64,827₹74.9 crore
Current progress
Work Tendered for the Part FS obtained for Cumbummettu to Njondickal. KSEB utility shifting estimate submitted to PD on 23/05/2022. Subproject revision file initiated on 18.03.2022 and is under scrutiny at KIIFB.

Money trail

Estimated amount
₹99,82,11,663₹99.82 crore
Expenditure reported
₹80,62,03,59280.8% of the estimated amount

Details

Project code
PWD006-11-02
Department
Public Works
Constituency
UdumbancholaMLA: Shri M. M. Mani

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvement to Ramakkalmedu - Cumbummedu Vannapuram Road- Part 1- Cumbummedu To Njondical- 28.1km”.

Approved
₹99,82,11,663₹99.82 crore
Paid so far
₹94,44,43,41594.6% of the amount approved

This package

Work awarded
₹91.75 crorepaid
₹97.09 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026