Ramakkalmedu-CVannapuram Road
Completed99%Physical progress
101.4%Financial progress
Scheduled start25-02-2023
Scheduled completion24-09-2025
- Contractor
- M/s . Theruvath Builders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹97,09,19,643₹97.09 crore
- Amount paid
- ₹90,91,24,498₹90.91 crore
- Paid to contractor
- ₹78,84,49,269₹78.84 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹99,82,11,663₹99.82 crore
- Technical sanction (TS)
- ₹97,12,29,392₹97.12 crore
- Tender amount
- ₹74,89,64,827₹74.9 crore
- Current progress
- Work Tendered for the Part FS obtained for Cumbummettu to Njondickal. KSEB utility shifting estimate submitted to PD on 23/05/2022. Subproject revision file initiated on 18.03.2022 and is under scrutiny at KIIFB.