Adkkaputhur - Kalluvazhi road
Completed100%Physical progress
97.8%Financial progress
Scheduled start01-10-2018
Scheduled completion06-12-2023
- Contractor
- Afsaln
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹15,20,80,509₹15.21 crore
- Amount paid
- ₹14,87,78,339₹14.88 crore
- Paid to contractor
- ₹13,94,38,045₹13.94 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹16,35,89,298₹16.36 crore
- Technical sanction (TS)
- ₹16,35,89,298₹16.36 crore
- Tender amount
- ₹13,25,14,587₹13.25 crore
- Letter of acceptance (LOA)
- ₹13,25,14,588₹13.25 crore
- Current progress
- First layer taring DBM & Final Layer Taring BC completed in full length.Drain and Culvert works 95% completed.Laying of interlock paver block on sholuder completed Hard shoulder works and Traffic safety works ongoing at site. 90% physical progress