Kanakkuമലയാളം
PWD006-15-01 Shornur

Adakkaputhur Kalluvazhi Road km 0/000 to 5/550 in Palakkad District- Contract work

Estimated amount

₹16.36 crore

₹16,35,89,298 · ₹14.29 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Adkkaputhur - Kalluvazhi road

Completed
100%Physical progress
97.8%Financial progress
Scheduled start01-10-2018
Scheduled completion06-12-2023
Contractor
Afsaln
Implementing agency (SPV)
KRFB
Contract amount
₹15,20,80,509₹15.21 crore
Amount paid
₹14,87,78,339₹14.88 crore
Paid to contractor
₹13,94,38,045₹13.94 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹16,35,89,298₹16.36 crore
Technical sanction (TS)
₹16,35,89,298₹16.36 crore
Tender amount
₹13,25,14,587₹13.25 crore
Letter of acceptance (LOA)
₹13,25,14,588₹13.25 crore
Current progress
First layer taring DBM & Final Layer Taring BC completed in full length.Drain and Culvert works 95% completed.Laying of interlock paver block on sholuder completed Hard shoulder works and Traffic safety works ongoing at site. 90% physical progress

Money trail

Estimated amount
₹16,35,89,298₹16.36 crore
Expenditure reported
₹14,28,91,98087.3% of the estimated amount

Details

Project code
PWD006-15-01
Department
Public Works
Constituency
ShornurMLA: Shri P. Mammikutty

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvemnts to Adakkaputhur Kalluvazhi Road km 0/000 to 5/550 in Palakkad District”.

Approved
₹16,35,89,298₹16.36 crore
Paid so far
₹16,02,87,12898% of the amount approved

This package

Work awarded
₹14.88 crorepaid
₹15.21 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…