Pathamkulam-Vaniyamkulam Road
Terminated89%Physical progress
66.6%Financial progress
Scheduled start16-10-2018
Scheduled completion31-08-2022
- Contractor
- M/s Deens Constructions
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹14,78,78,206₹14.79 crore
- Amount paid
- ₹9,84,70,171₹9.85 crore
- Paid to contractor
- ₹8,97,38,287₹8.97 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹23,13,10,735₹23.13 crore
- Technical sanction (TS)
- ₹20,56,00,000₹20.56 crore
- Tender amount
- ₹17,36,07,501₹17.36 crore
- Letter of acceptance (LOA)
- ₹17,36,07,501₹17.36 crore
- Current progress
- First layer taring BM completed in full strech of road 6km.Retaing wall and culvert completed 85% Second layer taring BC laying Planning to complete after rainy season.