Kanakkuമലയാളം
PWD006-16-01 Shornur

Development of 43 Roads

Total of works

₹23.13 crore

₹23,13,10,735

Stage

Terminated

Status of the works, as KIIFB records it.

Location

Works (1)

Pathamkulam-Vaniyamkulam Road

Terminated
89%Physical progress
66.6%Financial progress
Scheduled start16-10-2018
Scheduled completion31-08-2022
Implementing agency (SPV)
KRFB
Contract amount
₹14,78,78,206₹14.79 crore
Amount paid
₹9,84,70,171₹9.85 crore
Paid to contractor
₹8,97,38,287₹8.97 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹23,13,10,735₹23.13 crore
Technical sanction (TS)
₹20,56,00,000₹20.56 crore
Tender amount
₹17,36,07,501₹17.36 crore
Letter of acceptance (LOA)
₹17,36,07,501₹17.36 crore
Current progress
First layer taring BM completed in full strech of road 6km.Retaing wall and culvert completed 85% Second layer taring BC laying Planning to complete after rainy season.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹23,13,10,735₹23.13 crore

Details

Project code
PWD006-16-01
Department
Public Works
Constituency
Shornur

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026