Kalladukka-Cherkala Road
Foreclosed80.4%Physical progress
78.1%Financial progress
Scheduled start17-10-2018
Scheduled completion30-11-2022
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹35,68,01,761₹35.68 crore
- Amount paid
- ₹27,87,11,193₹27.87 crore
- Paid to contractor
- ₹25,83,89,153₹25.84 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹39,76,00,000₹39.76 crore
- Technical sanction (TS)
- ₹57,30,000₹57.3 lakh
- Tender amount
- ₹35,68,01,761₹35.68 crore
- Letter of acceptance (LOA)
- ₹35,68,01,761₹35.68 crore
- Current progress
- Full stretch DGBM work completed and achieved a physical progress of about 78%.