PWD006-21-01 Mannarkkad

MES College Payyanadam Road KM 0/000-8/000- Contract work

Estimated amount

₹21.57 crore

₹21,57,00,000 · ₹14.79 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

MES college-Payyanadam Road

Completed
100%Physical progress
100%Financial progress
Scheduled start01-10-2018
Scheduled completion30-05-2025
Implementing agency (SPV)
KRFB
Contract amount
₹15,57,16,910₹15.57 crore
Amount paid
₹15,57,16,909₹15.57 crore
Paid to contractor
₹14,44,92,828₹14.45 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹21,57,00,000₹21.57 crore
Technical sanction (TS)
₹21,49,00,000₹21.49 crore
Tender amount
₹16,42,23,426₹16.42 crore
Letter of acceptance (LOA)
₹16,42,23,426₹16.42 crore
Current progress
BC work Completed for Entire Strech.Physical Progress of Work-90%. Road marking, Road signages and Irish drain work pending

Money trail

Estimated amount
₹21,57,00,000₹21.57 crore
Expenditure reported
₹14,79,31,02768.6% of the estimated amount

Details

Project code
PWD006-21-01
Department
Public Works
Constituency
Mannarkkad

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Widening & Providing BM& BC TO MES College Payyanadam Road KM 0/000-8/000 in Palakkad District”.

Approved
₹21,57,00,000₹21.57 crore
Paid so far
₹16,90,66,33478.4% of the amount approved

This package

Work awarded
₹15.57 crorepaid
₹15.57 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet