Kanakkuമലയാളം
PWD006-22-01 Kanhangad

Kiliyalam - Varanhoor Road - Contract work

Spent on this package so far

₹22.9 crore

₹22,90,06,955

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Works (1)

Kiliyalam - Varanhoor Road

Completed
100%Physical progress
95.8%Financial progress
Scheduled start17-01-2019
Scheduled completion05-11-2025
Implementing agency (SPV)
KRFB
Contract amount
₹24,64,95,361₹24.65 crore
Amount paid
₹24,09,13,475₹24.09 crore
Paid to contractor
₹22,29,84,119₹22.3 crore
Administrative sanction (AS)
₹24,00,00,000₹24 crore
Financial sanction (FS)
₹30,17,23,000₹30.17 crore
Technical sanction (TS)
₹23,18,00,000₹23.18 crore
Tender amount
₹25,14,66,273₹25.15 crore
Letter of acceptance (LOA)
₹25,14,66,273₹25.15 crore
Current progress
DBM work for the whole 10km road has been completed . The concrete works for protection walls and Precast drain workss are in progress and achieved about 77% progress.

Money trail

Estimated amount
₹30,17,23,000Estimate of sub-project PWD006-22, shared by 2 contract packages
Expenditure reported · this package
₹22,90,06,955
Expenditure reported · all 2 packages
₹26,45,58,93987.7% of the estimated amount

Details

Project code
PWD006-22-01
Department
Public Works
Constituency
Kanhangad

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements and providing DBM and BC to Kiliyalam- Varanhoor road KM 0/000 to 10/000 in Kasargod District”. The figures below are for that whole project, not this package alone.

Approved
₹30,17,23,000₹30.17 crore
Paid so far
₹29,29,00,45297.1% of the amount approved

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project