Kongad-Mannarakad-Tippu Sultan road
In progress100%Physical progress
97.5%Financial progress
Scheduled start08-03-2021
Scheduled completion07-12-2024
- Contractor
- M/s Malabar Tech
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹60,23,65,028₹60.24 crore
- Amount paid
- ₹58,70,96,052₹58.71 crore
- Paid to contractor
- ₹54,97,80,567₹54.98 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹66,81,16,582₹66.81 crore
- Technical sanction (TS)
- ₹66,81,16,582₹66.81 crore
- Tender amount
- ₹51,33,07,822₹51.33 crore
- Letter of acceptance (LOA)
- ₹51,33,07,822₹51.33 crore
- Current progress
- Physical progress 12 %. For the first 5 km culvert and retaining wall works ongoing.