Total of works

₹25.45 crore

₹25,44,50,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kanjikode Industrial Estate Mupana road

Scheduled completion was 13-01-2026. That was 262 days ago, and KIIFB lists the status as “Approved”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kanjikode Industrial Estate Mupana road

Approved
25%Physical progress
12.7%Financial progress
Scheduled start13-10-2024
Scheduled completion13-01-2026
Implementing agency (SPV)
KRFB
Contract amount
₹23,27,30,453₹23.27 crore
Amount paid
₹2,94,59,272₹2.95 crore
Paid to contractor
₹2,75,86,850₹2.76 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹25,44,50,000₹25.45 crore
Technical sanction (TS)
₹25,44,50,000₹25.45 crore
Tender amount
₹23,27,30,453₹23.27 crore
Current progress
TS estimate placed on 67th Technical Committee Meeting held on 12.11.2020. Committee directed to submit estimate after complying recommendations in DAR. Estimate placed on 99th TC held on 4.4.2022. Vide letter dated 19.1.2022, it was requested to carry o

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹25,44,50,000₹25.45 crore

Details

Project code
PWD006-30
Department
Public Works
Constituency
Malampuzha

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…