Kanjikode Industrial Estate Mupana road
Approved25%Physical progress
12.7%Financial progress
Scheduled start13-10-2024
Scheduled completion13-01-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹23,27,30,453₹23.27 crore
- Amount paid
- ₹2,94,59,272₹2.95 crore
- Paid to contractor
- ₹2,75,86,850₹2.76 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹25,44,50,000₹25.45 crore
- Technical sanction (TS)
- ₹25,44,50,000₹25.45 crore
- Tender amount
- ₹23,27,30,453₹23.27 crore
- Current progress
- TS estimate placed on 67th Technical Committee Meeting held on 12.11.2020. Committee directed to submit estimate after complying recommendations in DAR. Estimate placed on 99th TC held on 4.4.2022. Vide letter dated 19.1.2022, it was requested to carry o