Para Mannukad Panampully road bridge
In progress100%Physical progress
51.3%Financial progress
Scheduled start05-02-2021
Scheduled completion15-11-2025
- Contractor
- M. Kunhimuhammed
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹9,34,79,472₹9.35 crore
- Amount paid
- ₹4,79,94,653₹4.8 crore
- Paid to contractor
- ₹4,53,26,603₹4.53 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹9,57,11,128₹9.57 crore
- Technical sanction (TS)
- ₹8,60,00,000₹8.6 crore
- Tender amount
- ₹9,34,79,472₹9.35 crore
- Letter of acceptance (LOA)
- ₹9,34,79,472₹9.35 crore
- Current progress
- Site handed over to contractor. Material source approved. Part Initial levels reported between ch. 0/090 and 0/400. Bridge Foundation and substructure works completed. Girder construction in progress. 3/9 girders constructed. River side protection wall