PWD006-31-01 Malampuzha

Construction of Para Mannukad Panampully Road Bridge Across Korayar in Malampuzha Constituency in Palakkad District - Contract

Estimated amount

₹9.57 crore

₹9,57,11,128 · ₹6.54 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Para Mannukad Panampully road bridge

Scheduled completion was 15-11-2025. That was 322 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Para Mannukad Panampully road bridge

In progress
100%Physical progress
51.3%Financial progress
Scheduled start05-02-2021
Scheduled completion15-11-2025
Implementing agency (SPV)
KRFB
Contract amount
₹9,34,79,472₹9.35 crore
Amount paid
₹4,79,94,653₹4.8 crore
Paid to contractor
₹4,53,26,603₹4.53 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹9,57,11,128₹9.57 crore
Technical sanction (TS)
₹8,60,00,000₹8.6 crore
Tender amount
₹9,34,79,472₹9.35 crore
Letter of acceptance (LOA)
₹9,34,79,472₹9.35 crore
Current progress
Site handed over to contractor. Material source approved. Part Initial levels reported between ch. 0/090 and 0/400. Bridge Foundation and substructure works completed. Girder construction in progress. 3/9 girders constructed. River side protection wall

Money trail

Estimated amount
₹9,57,11,128₹9.57 crore
Expenditure reported
₹6,53,86,63068.3% of the estimated amount

Details

Project code
PWD006-31-01
Department
Public Works
Constituency
Malampuzha
Name as KIIFB publishes it
CONSTRUCTION OF PARA MANNUKAD PANAMPULLY ROAD BRIDGE ACROSS KORAYAR IN MALAMPUZHA CONSTITUENCY IN PALAKKAD DISTRICT - Contract

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of Para Mannukad Panampully Road Bridge Across Korayar in Malampuzha Constituency in Palakkad District”.

Approved
₹9,57,11,128₹9.57 crore
Paid so far
₹7,01,74,03573.3% of the amount approved

This package

Work started
₹6.79 crorepaid
₹8.32 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…