Vallapuzha ROB
Approved0%Physical progress
Not publishedFinancial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹68,00,00,000₹68 crore
- Financial sanction (FS)
- ₹23,28,41,802₹23.28 crore
- Technical sanction (TS)
- ₹20,83,35,362₹20.83 crore
- Tender amount
- ₹23,93,87,544₹23.94 crore
- Current progress
- LA requisition submitted on 16.08.2019 and AS for LA received from Revenue Department on 17.09.2019. Boundary Stone Planting completed and Joint site inspection conducted. GAD Approved & Estimate for approach portion submitted to Railways for approval on