Kanakkuമലയാളം

Total of works

₹40.64 crore

₹40,63,79,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Hosangadi ROB

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹8,78,00,00,000₹878 crore
Financial sanction (FS)
₹40,63,79,000₹40.64 crore
Current progress
LA plan under preparation. The requisition will be submitted to District Collector after the approval of GAD from Railways. A joint site inspection was carried out with NHAI and ULCCS representative on 18.10.2021 at Hosangadi. On 20.10.2021 NHAI sent a

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹40,63,79,000₹40.64 crore

Details

Project code
PWD011-13
Department
Public Works
Constituency
Manjeshwaram

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Hosangadi ROB
  • Scheduled start and completion dates · Hosangadi ROB
  • Amount paid · Hosangadi ROB

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256