Moru glass gate, near IIT Palakkad ROB
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹8,78,00,00,000₹878 crore
- Financial sanction (FS)
- ₹33,19,14,000₹33.19 crore
- Current progress
- After several revisions, final GAD submitted to Railways on 31.08.2021. Reminder letter for approval of GADs submitted to Chief Administrative Officer, Southern Railway, Ernakulam and Chief Engineer (RSW), Sothern Railway, Chennai on 30.06.2022. On 11.0