Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹8,78,00,00,000₹878 crore
- Financial sanction (FS)
- ₹39,09,40,000₹39.09 crore
- Current progress
- DPR approved by KIIFB on 04.09.2021. GAD was approved by Railways on 26.02.2022. LA requisition submitted to District Collector Kottayam on 13.04.2022. LAO appointed. Revenue Sanction for LA received as per G.O.( Rt) No. 2082/2022/RD dated 07.05.2022. 6(