Kuttikanam to Chappathu Road
Completed100%Physical progress
99.9%Financial progress
Scheduled start09-09-2020
Scheduled completion29-02-2024
- Contractor
- M/s . Theruvath Builders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,05,44,82,706₹105.45 crore
- Amount paid
- ₹1,05,29,56,163₹105.3 crore
- Paid to contractor
- ₹98,44,48,633₹98.44 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹1,07,69,61,187₹107.7 crore
- Technical sanction (TS)
- ₹10,54,48,22,710₹1,054.48 crore
- Tender amount
- ₹77,02,52,307₹77.03 crore
- Letter of acceptance (LOA)
- ₹77,02,52,307₹77.03 crore
- Current progress
- Work in progress