Total of works

₹107.7 crore

₹1,07,69,61,187

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Kuttikanam to Chappathu Road

Completed
100%Physical progress
99.9%Financial progress
Scheduled start09-09-2020
Scheduled completion29-02-2024
Implementing agency (SPV)
KRFB
Contract amount
₹1,05,44,82,706₹105.45 crore
Amount paid
₹1,05,29,56,163₹105.3 crore
Paid to contractor
₹98,44,48,633₹98.44 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹1,07,69,61,187₹107.7 crore
Technical sanction (TS)
₹10,54,48,22,710₹1,054.48 crore
Tender amount
₹77,02,52,307₹77.03 crore
Letter of acceptance (LOA)
₹77,02,52,307₹77.03 crore
Current progress
Work in progress

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,07,69,61,187₹107.7 crore

Details

Project code
PWD013-04-02
Department
Public Works
Constituency
Peerumade

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026