Nandarapadvu to Chevar
Completed100%Physical progress
98.3%Financial progress
Scheduled start18-06-2018
Scheduled completion31-10-2023
- Contractor
- M/s . K. K. Builders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹53,85,29,137₹53.85 crore
- Amount paid
- ₹52,94,38,296₹52.94 crore
- Paid to contractor
- ₹49,00,85,804₹49.01 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹54,76,00,000₹54.76 crore
- Technical sanction (TS)
- ₹59,41,21,826₹59.41 crore
- Tender amount
- ₹49,42,41,651₹49.42 crore
- Letter of acceptance (LOA)
- ₹49,42,41,651₹49.42 crore
- Current progress
- Work completed