Total of works

₹63.78 crore

₹63,78,10,000

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Mananthavady - Arunapuzha

Scheduled completion was 19-01-2026. That was 256 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Mananthavady - Arunapuzha

In progress
55%Physical progress
31.9%Financial progress
Scheduled start20-07-2024
Scheduled completion19-01-2026
Implementing agency (SPV)
KRFB
Contract amount
₹43,07,19,828₹43.07 crore
Amount paid
₹13,74,07,767₹13.74 crore
Paid to contractor
₹12,86,74,219₹12.87 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹63,78,10,000₹63.78 crore
Technical sanction (TS)
₹34,63,21,331₹34.63 crore
Tender amount
₹43,07,19,828₹43.07 crore
Current progress
Work in progress for 16.75km. Remaining stretch is being developed as another KIIFB work (12.25km). 12.1km DPR not prepared as the road was in DLP period. Now the work in standstill stage.WP(c) filed by the firm.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹63,78,10,000₹63.78 crore

Details

Project code
PWD013-13-04
Department
Public Works
Constituency
Kalpetta

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org