Mananthavady - Arunapuzha
In progress55%Physical progress
31.9%Financial progress
Scheduled start20-07-2024
Scheduled completion19-01-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹43,07,19,828₹43.07 crore
- Amount paid
- ₹13,74,07,767₹13.74 crore
- Paid to contractor
- ₹12,86,74,219₹12.87 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹63,78,10,000₹63.78 crore
- Technical sanction (TS)
- ₹34,63,21,331₹34.63 crore
- Tender amount
- ₹43,07,19,828₹43.07 crore
- Current progress
- Work in progress for 16.75km. Remaining stretch is being developed as another KIIFB work (12.25km). 12.1km DPR not prepared as the road was in DLP period. Now the work in standstill stage.WP(c) filed by the firm.