PWD013-15-04 Udumbanchola

HILL HIGHWAY - Improvements to Peerumade Devikulam road km 19/000 to 40/050 and Thodupuzha Puliyanmala road km 85/500 to 92/167 in Idukki District- TS2 Work Contract

Spent on this package so far

₹12.85 crore

₹12,84,53,067

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Nariampara - Idukki Kavala (36/625 - 39/525)

Completed
100%Physical progress
69.8%Financial progress
Scheduled start24-02-2023
Scheduled completion28-02-2025
Implementing agency (SPV)
KRFB
Contract amount
₹19,20,49,159₹19.2 crore
Amount paid
₹13,41,36,848₹13.41 crore
Paid to contractor
₹12,56,11,185₹12.56 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹1,44,09,50,000₹144.1 crore
Technical sanction (TS)
₹21,64,60,000₹21.65 crore
Tender amount
₹19,20,49,159₹19.2 crore
Letter of acceptance (LOA)
₹17,14,72,463₹17.15 crore

Money trail

Estimated amount
₹1,75,67,03,765Estimate of sub-project PWD013-14, shared by 3 contract packages
Expenditure reported · this package
₹12,84,53,067
Expenditure reported · all 3 packages
₹1,01,99,44,40358.1% of the estimated amount

Details

Project code
PWD013-15-04
Department
Public Works
Constituency
UdumbancholaMLA: Shri M. M. Mani

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project