Kolichal - Cherupuzha Road
Foreclosed99.4%Physical progress
88.1%Financial progress
Scheduled start05-03-2019
Scheduled completion31-12-2024
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹77,37,90,583₹77.38 crore
- Amount paid
- ₹68,13,82,363₹68.14 crore
- Paid to contractor
- ₹63,13,19,719₹63.13 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹89,24,27,188₹89.24 crore
- Technical sanction (TS)
- ₹1,63,99,863₹1.64 crore
- Tender amount
- ₹77,37,90,583₹77.38 crore
- Letter of acceptance (LOA)
- ₹77,37,90,583₹77.38 crore
- Current progress
- Ongoing work. Revised estmate including provision for execution of road work in forest portion is under process