Kolichal - Edaparamba Road
Foreclosed100%Physical progress
70.1%Financial progress
Scheduled start03-07-2018
Scheduled completion30-09-2022
- Contractor
- T. A. Abdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹73,98,56,623₹73.99 crore
- Amount paid
- ₹51,83,57,533₹51.84 crore
- Paid to contractor
- ₹48,43,71,354₹48.44 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹85,15,00,000₹85.15 crore
- Technical sanction (TS)
- ₹85,15,00,000₹85.15 crore
- Tender amount
- ₹73,98,56,623₹73.99 crore
- Letter of acceptance (LOA)
- ₹73,98,56,623₹73.99 crore
- Current progress
- Road Work in progress. Pallanchi bridge (1&2) DPR submitted as separate work for FS.