Kottiyoor Boys town road
In progress93%Physical progress
85.7%Financial progress
Scheduled start23-06-2022
Scheduled completion22-06-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,18,86,54,971₹118.87 crore
- Amount paid
- ₹1,01,87,43,993₹101.87 crore
- Paid to contractor
- ₹95,39,93,235₹95.4 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹1,86,65,02,033₹186.65 crore
- Technical sanction (TS)
- ₹1,23,60,47,000₹123.6 crore
- Tender amount
- ₹1,18,86,54,971₹118.87 crore
- Letter of acceptance (LOA)
- ₹1,06,12,99,080₹106.13 crore
- Current progress
- Agreement executed on 06.06.2022