Total of works

₹186.65 crore

₹1,86,65,02,033

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kottiyoor Boys town road

Scheduled completion was 22-06-2025. That was 467 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kottiyoor Boys town road

In progress
93%Physical progress
85.7%Financial progress
Scheduled start23-06-2022
Scheduled completion22-06-2025
Implementing agency (SPV)
KRFB
Contract amount
₹1,18,86,54,971₹118.87 crore
Amount paid
₹1,01,87,43,993₹101.87 crore
Paid to contractor
₹95,39,93,235₹95.4 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹1,86,65,02,033₹186.65 crore
Technical sanction (TS)
₹1,23,60,47,000₹123.6 crore
Tender amount
₹1,18,86,54,971₹118.87 crore
Letter of acceptance (LOA)
₹1,06,12,99,080₹106.13 crore
Current progress
Agreement executed on 06.06.2022

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,86,65,02,033₹186.65 crore

Details

Project code
PWD013-24-01
Department
Public Works
Constituency
Mananthavady

What we don't know yet