Work 1
In progress64.3%Physical progress
38.3%Financial progress
Scheduled start03-02-2023
Scheduled completion02-11-2025
- Contractor
- Ahammedharisb
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹40,96,81,212₹40.97 crore
- Amount paid
- ₹15,68,03,584₹15.68 crore
- Paid to contractor
- ₹14,81,66,050₹14.82 crore
- Administrative sanction (AS)
- ₹35,00,00,00,000₹3,500 crore
- Financial sanction (FS)
- ₹39,79,71,300₹39.8 crore
- Technical sanction (TS)
- ₹40,96,81,212₹40.97 crore
- Tender amount
- ₹38,90,29,717₹38.9 crore
- Letter of acceptance (LOA)
- ₹34,73,47,961₹34.73 crore