Total of works

₹39.8 crore

₹39,79,71,300

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · #1

Scheduled completion was 02-11-2025. That was 334 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Work 1

In progress
64.3%Physical progress
38.3%Financial progress
Scheduled start03-02-2023
Scheduled completion02-11-2025
Contractor
Ahammedharisb
Implementing agency (SPV)
KRFB
Contract amount
₹40,96,81,212₹40.97 crore
Amount paid
₹15,68,03,584₹15.68 crore
Paid to contractor
₹14,81,66,050₹14.82 crore
Administrative sanction (AS)
₹35,00,00,00,000₹3,500 crore
Financial sanction (FS)
₹39,79,71,300₹39.8 crore
Technical sanction (TS)
₹40,96,81,212₹40.97 crore
Tender amount
₹38,90,29,717₹38.9 crore
Letter of acceptance (LOA)
₹34,73,47,961₹34.73 crore

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹39,79,71,300₹39.8 crore

Details

Project code
PWD013-33-01
Department
Public Works
Constituency
Udumbanchola

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…