PWD015-102-02 Kanhangad

Project - Construction of Padanakkad - Vellarikundu Road in Kasargod District - Phase - I, Pulikkal Bridge, Anappetty Bridge and Banam Culvert - Contract

Estimated amount

₹9.38 crore

₹9,37,55,229 · ₹2.84 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Flags (1)

Overdue · Padannakkad over Bridge

Scheduled completion was 18-12-2025. That was 288 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Padannakkad over Bridge

In progress
65.3%Physical progress
32.1%Financial progress
Scheduled start19-09-2023
Scheduled completion18-12-2025
Contractor
TAAbdul Rahiman
Implementing agency (SPV)
KRFB
Contract amount
₹9,15,35,926₹9.15 crore
Amount paid
₹2,94,08,222₹2.94 crore
Paid to contractor
₹2,77,88,268₹2.78 crore
Administrative sanction (AS)
₹60,00,00,000₹60 crore
Financial sanction (FS)
₹9,37,55,229₹9.38 crore
Technical sanction (TS)
₹9,25,35,353₹9.25 crore
Tender amount
₹9,15,35,926₹9.15 crore
Current progress
Part FS and TS obtained for Construction of Pulikkal Bridge, Anapetty bridge and banam culvert. Bridge works tendered, Financial bid opened on 5/4/2022 and is under process for bridge works. TAR reply for road part Sub project revision including road wo

Money trail

Estimated amount
₹9,37,55,229₹9.38 crore
Expenditure reported
₹2,84,11,32330.3% of the estimated amount

Details

Project code
PWD015-102-02
Department
Public Works
Constituency
KanhangadMLA: Shri E. Chandrasekharan
Name as KIIFB publishes it
KIIFB Project - Construction of Padanakkad - Vellarikundu Road in Kasargod District - Phase - I, Pulikkal Bridge, Anappetty Bridge and Banam Culvert - Contract

What KIIFB approved and paid

On KIIFB's project status page this belongs to “2017-18 Improvements by providing DBM and BC Padannakkad over Bridge-Vellarikundu road Km 0/000 to 31/100 in Kasargod District”.

Approved
₹9,37,55,229₹9.38 crore
Paid so far
₹6,71,05,62371.6% of the amount approved

This package

Work awarded
₹6.58 crorepaid
₹9.15 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…