Padannakkad over Bridge
In progress65.3%Physical progress
32.1%Financial progress
Scheduled start19-09-2023
Scheduled completion18-12-2025
- Contractor
- TAAbdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹9,15,35,926₹9.15 crore
- Amount paid
- ₹2,94,08,222₹2.94 crore
- Paid to contractor
- ₹2,77,88,268₹2.78 crore
- Administrative sanction (AS)
- ₹60,00,00,000₹60 crore
- Financial sanction (FS)
- ₹9,37,55,229₹9.38 crore
- Technical sanction (TS)
- ₹9,25,35,353₹9.25 crore
- Tender amount
- ₹9,15,35,926₹9.15 crore
- Current progress
- Part FS and TS obtained for Construction of Pulikkal Bridge, Anapetty bridge and banam culvert. Bridge works tendered, Financial bid opened on 5/4/2022 and is under process for bridge works. TAR reply for road part Sub project revision including road wo