Total of works

₹29.49 crore

₹29,49,00,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Kottayam-Kumarakom road

Reported financial progress is 62% and reported physical progress is 0%, a gap of 62 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Kottayam-Kumarakom road

Approved
0%Physical progress
62%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
₹15,68,00,000₹15.68 crore
Amount paid
₹9,72,00,000₹9.72 crore
Paid to contractor
₹9,10,00,000₹9.1 crore
Administrative sanction (AS)
₹1,20,00,00,000₹120 crore
Financial sanction (FS)
₹29,49,00,000₹29.49 crore
Technical sanction (TS)
₹8,29,00,000₹8.29 crore
Tender amount
₹8,09,00,000₹8.09 crore
Letter of acceptance (LOA)
₹6,85,00,000₹6.85 crore
Current progress
ROAD : Replies to TAR submitted to Project Director, KRFB and the work is in appraisal stage. Land to be Acquired Bridge: IMPROVEMENTS TO KOTTAYAM-KUMARAKOM ROAD (ILLICKAL TO KAIPUZHAMUTTU) - CONSTRUCTION OF KARIKKATHARA BRIDGE Part FS obtained for Kari

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹29,49,00,000₹29.49 crore

Details

Project code
PWD015-103
Department
Public Works
Constituency
Ettumanoor

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Kottayam-Kumarakom road
  • Scheduled start and completion dates · Kottayam-Kumarakom road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…