Kottayam-Kumarakom road
In progress86.1%Physical progress
83.3%Financial progress
Scheduled start27-06-2022
Scheduled completion31-10-2025
- Contractor
- M/s Perumalil Granite Constructions
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹18,48,91,685₹18.49 crore
- Amount paid
- ₹15,40,04,102₹15.4 crore
- Paid to contractor
- ₹14,42,15,629₹14.42 crore
- Administrative sanction (AS)
- ₹1,20,00,00,000₹120 crore
- Financial sanction (FS)
- ₹29,49,00,000₹29.49 crore
- Technical sanction (TS)
- ₹18,48,91,685₹18.49 crore
- Tender amount
- ₹8,08,78,787₹8.09 crore
- Letter of acceptance (LOA)
- ₹6,85,41,345₹6.85 crore
- Current progress
- ROAD : Replies to TAR submitted to Project Director, KRFB and the work is in appraisal stage. Land to be Acquired Bridge: IMPROVEMENTS TO KOTTAYAM-KUMARAKOM ROAD (ILLICKAL TO KAIPUZHAMUTTU) - CONSTRUCTION OF KARIKKATHARA BRIDGE Part FS obtained for Kari