Total of works

₹29.49 crore

₹29,49,00,000

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kottayam-Kumarakom road

Scheduled completion was 31-10-2025. That was 336 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kottayam-Kumarakom road

In progress
86.1%Physical progress
83.3%Financial progress
Scheduled start27-06-2022
Scheduled completion31-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹18,48,91,685₹18.49 crore
Amount paid
₹15,40,04,102₹15.4 crore
Paid to contractor
₹14,42,15,629₹14.42 crore
Administrative sanction (AS)
₹1,20,00,00,000₹120 crore
Financial sanction (FS)
₹29,49,00,000₹29.49 crore
Technical sanction (TS)
₹18,48,91,685₹18.49 crore
Tender amount
₹8,08,78,787₹8.09 crore
Letter of acceptance (LOA)
₹6,85,41,345₹6.85 crore
Current progress
ROAD : Replies to TAR submitted to Project Director, KRFB and the work is in appraisal stage. Land to be Acquired Bridge: IMPROVEMENTS TO KOTTAYAM-KUMARAKOM ROAD (ILLICKAL TO KAIPUZHAMUTTU) - CONSTRUCTION OF KARIKKATHARA BRIDGE Part FS obtained for Kari

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹29,49,00,000₹29.49 crore

Details

Project code
PWD015-103-01
Department
Public Works
Constituency
Ettumanoor

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026