Kanjirappalli - Manimala - Kulathurmozhi - Karshaka Souhruda Link road
Approved1%Physical progress
Not publishedFinancial progress
Scheduled start04-05-2025
Scheduled completion04-11-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹88,82,70,106₹88.83 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹85,81,98,699₹85.82 crore
- Technical sanction (TS)
- ₹83,89,15,767₹83.89 crore
- Tender amount
- ₹88,82,70,106₹88.83 crore
- Current progress
- FS obtained for Rs. 79.11 crore on 20.03.2022. .Work for planting boundary stone,agreement executed and work started. Joint inspection with KWA and KSEB for the preparation of utility shifting estimate completed. Procdure for getting free surrended lan