Various Roads in Cherthala
Approved0%Physical progress
0%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- KRFB
- Contract amount
- Not published
- Amount paid
- Not published
- Financial sanction (FS)
- ₹20,61,00,000₹20.61 crore
- Current progress
- Non feasibility for the draft alignment- submitted to DRIQ.Rev DPR submitted for Rs.19.46 Cr submitted to TL on 30.6.22