Kanakkuമലയാളം

Total of works

₹41.73 crore

₹41,73,37,709

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kakkavayal Kolavayal Road

Scheduled completion was 28-12-2025. That was 278 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kakkavayal Kolavayal Road

In progress
68%Physical progress
46.7%Financial progress
Scheduled start30-09-2023
Scheduled completion28-12-2025
Implementing agency (SPV)
KRFB
Contract amount
₹30,82,47,789₹30.82 crore
Amount paid
₹14,38,66,755₹14.39 crore
Paid to contractor
₹13,59,41,873₹13.59 crore
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Financial sanction (FS)
₹41,73,37,709₹41.73 crore
Technical sanction (TS)
₹31,95,75,887₹31.96 crore
Tender amount
₹30,82,47,789₹30.82 crore
Current progress
Tender opened on 29-03-2022 and Tender Evaluation in progress.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹41,73,37,709₹41.73 crore

Details

Project code
PWD015-18-01
Department
Public Works
Constituency
Sulthanbathery,Kalpetta

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…