Kappiset Payyampally Road
Completed100%Physical progress
94.1%Financial progress
Scheduled start15-11-2022
Scheduled completion30-04-2024
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹52,07,62,076₹52.08 crore
- Amount paid
- ₹49,01,58,812₹49.02 crore
- Paid to contractor
- ₹45,81,40,119₹45.81 crore
- Financial sanction (FS)
- ₹55,25,17,054₹55.25 crore
- Technical sanction (TS)
- ₹52,07,62,076₹52.08 crore
- Tender amount
- ₹44,86,81,013₹44.87 crore
- Letter of acceptance (LOA)
- ₹40,06,08,047₹40.06 crore
- Current progress
- Drain work completed for 5000 m. subgrade 13k m completed, GSB 13km completed, WMM 13Km completed.DBM 13km completed. All culvert completed . DR 4900 m completed.Work in good progress.