Badiadka Yethadka Soolyapadhavu Road
Completed100%Physical progress
94.1%Financial progress
Scheduled start31-12-2019
Scheduled completion31-01-2023
- Contractor
- ASSMASConstriuctions Pvt Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹40,54,58,218₹40.55 crore
- Amount paid
- ₹38,14,58,721₹38.15 crore
- Paid to contractor
- ₹35,61,09,388₹35.61 crore
- Administrative sanction (AS)
- ₹28,00,00,000₹28 crore
- Financial sanction (FS)
- ₹45,57,65,070₹45.58 crore
- Technical sanction (TS)
- ₹40,54,58,218₹40.55 crore
- Tender amount
- ₹40,13,36,617₹40.13 crore
- Letter of acceptance (LOA)
- ₹40,13,36,617₹40.13 crore
- Current progress
- Work is going in good progress and achieved almost 80% physical progress. Now 99% DBM laying work completed and BC work Completed for 4 km. And also, the Side protection work, Drainage work under progress. A financial progress of 60.00% achieved.