Sulthan Bathery- Cherambadi road
In progress93%Physical progress
77.6%Financial progress
Scheduled start29-02-2024
Scheduled completion28-08-2025
- Contractor
- M/s . Irikkur Construction Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹31,02,87,061₹31.03 crore
- Amount paid
- ₹24,08,03,428₹24.08 crore
- Paid to contractor
- ₹22,54,98,107₹22.55 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹46,93,70,000₹46.94 crore
- Technical sanction (TS)
- ₹26,34,60,346₹26.35 crore
- Tender amount
- ₹31,02,87,061₹31.03 crore
- Current progress
- Culvert,Subgrade, GSB, WMM and drain work in progress.