Total of works

₹58.3 crore

₹58,29,96,933

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Bovikanam - Kuttikol road

Completed
100%Physical progress
98.1%Financial progress
Scheduled start17-07-2020
Scheduled completion10-03-2025
Implementing agency (SPV)
KRFB
Contract amount
₹56,35,68,395₹56.36 crore
Amount paid
₹55,26,53,245₹55.27 crore
Paid to contractor
₹52,13,26,655₹52.13 crore
Financial sanction (FS)
₹58,29,96,933₹58.3 crore
Technical sanction (TS)
₹59,78,77,459₹59.79 crore
Tender amount
₹51,07,57,011₹51.08 crore
Letter of acceptance (LOA)
₹51,07,57,011₹51.08 crore
Current progress
Work completed.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹58,29,96,933₹58.3 crore

Details

Project code
PWD015-40-01
Department
Public Works
Constituency
Udma

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…