Nileswar- NH- Raja Road
In progress50%Physical progress
38.4%Financial progress
Scheduled start02-03-2024
Scheduled completion02-09-2025
- Contractor
- T. AAbdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹24,15,67,254₹24.16 crore
- Amount paid
- ₹9,27,97,867₹9.28 crore
- Paid to contractor
- ₹8,76,86,110₹8.77 crore
- Administrative sanction (AS)
- ₹40,00,00,000₹40 crore
- Financial sanction (FS)
- ₹40,90,80,941₹40.91 crore
- Technical sanction (TS)
- ₹23,28,37,661₹23.28 crore
- Tender amount
- ₹24,15,67,254₹24.16 crore
- Current progress
- The land acquisition work under progress for Raja Road deelopment. LA = 8.15 Crore Area = 1.50 Acre. Social impact assesment study conducted.Revenue department not yet issued the Details of building for which valuationn has to be carried out. Valuation i