PWD015-75-04 Kanjirappally

2017-18 Improvements to Pathanad Edayirikkappuzha road in Kottayam District-Contract

Spent on this package so far

₹23.39 crore

₹23,38,81,036

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Pathanad Edayirikkappuzha road

Scheduled completion was 22-07-2025. That was 437 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Pathanad Edayirikkappuzha road

In progress
67.3%Physical progress
49.2%Financial progress
Scheduled start22-01-2024
Scheduled completion22-07-2025
Contractor
Raji Mathew
Implementing agency (SPV)
KRFB
Contract amount
₹36,20,24,022₹36.2 crore
Amount paid
₹17,81,21,897₹17.81 crore
Paid to contractor
₹16,68,00,565₹16.68 crore
Financial sanction (FS)
₹38,52,26,123₹38.52 crore
Technical sanction (TS)
₹34,72,00,000₹34.72 crore
Tender amount
₹36,20,24,022₹36.2 crore
Current progress
.1.TS obtained for Rs. 33.681 Crores on 09/03/2022. Tender opened on 09-05-2022 and two bids have been recieved. PQ Evaluation done and single bid qualified. Revised alignment drawing following the existing centreline received.

Money trail

Estimated amount
₹38,52,26,123Estimate of sub-project PWD015-75, shared by 2 contract packages
Expenditure reported · this package
₹23,38,81,036
Expenditure reported · all 2 packages
₹23,38,81,03660.7% of the estimated amount

Details

Project code
PWD015-75-04
Department
Public Works
Constituency
KanjirappallyMLA: DR. N. Jayaraj
Name as KIIFB publishes it
KIIFB 2017-18 Improvements to Pathanad Edayirikkappuzha road in Kottayam District-Contract

What KIIFB approved and paid

On KIIFB's project status page this belongs to “2017-18 Improvements to Pathanad Edayirikkappuzha road in Kottayam District”. The figures below are for that whole project, not this package alone.

Approved
₹38,52,26,123₹38.52 crore
Paid so far
₹34,53,19,27989.6% of the amount approved

This package

Work awarded
₹32.73 crorepaid
₹36.2 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project