Ezhamkulam Kaipatoor Road
Completed96%Physical progress
74%Financial progress
Scheduled start06-10-2023
Scheduled completion15-06-2025
- Contractor
- M/s . Raji Mathew&Co.
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹60,92,95,072₹60.93 crore
- Amount paid
- ₹45,08,89,074₹45.09 crore
- Paid to contractor
- ₹42,22,30,834₹42.22 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹61,17,95,072₹61.18 crore
- Technical sanction (TS)
- ₹60,92,95,072₹60.93 crore
- Tender amount
- ₹48,65,65,132₹48.66 crore
- Current progress
- Work retendered and Contractors can participate upto 27/06/2022. Work tendered and contractor has taken the work . Patch work for 25 lakhs arranged for urgent rectification are going on. Topographic survey is completed and Monsoon rectification work is s