Total of works

₹30.55 crore

₹30,55,24,184

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Kuruppanthara ROB

Reported financial progress is 90.8% and reported physical progress is 0%, a gap of 90.8 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Kuruppanthara ROB

Approved
0%Physical progress
90.8%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
₹8,55,00,000₹8.55 crore
Administrative sanction (AS)
₹33,00,00,000₹33 crore
Financial sanction (FS)
₹30,55,24,184₹30.55 crore
Current progress
LA requisition submitted on 12.07.2018. 11(1) notification published on 16.07.2020. LA fund request was received from LAO on 11.03.2022 and uploaded in KIIFB portal. KIIFB directed to limit the 12% increase to 6 months and the revised proceeding uploaded

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹30,55,24,184₹30.55 crore

Details

Project code
PWD016-03
Department
Public Works
Constituency
Kaduthuruthy

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Kuruppanthara ROB
  • Scheduled start and completion dates · Kuruppanthara ROB

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026