Mambrakunnel ROB
Approved0%Physical progress
Not publishedFinancial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹60,00,00,000₹60 crore
- Financial sanction (FS)
- ₹36,15,32,727₹36.15 crore
- Technical sanction (TS)
- ₹24,02,70,095₹24.03 crore
- Tender amount
- ₹28,64,35,409₹28.64 crore
- Letter of acceptance (LOA)
- ₹24,27,41,872₹24.27 crore
- Current progress
- LA requisition submitted on 24.12.2018. 4(1) notification published on 27.12.2019. 11(1) Notification published on 23.01.2021. BVR approved on 08.11.2021. Structural valuation, RR Package under preparation. Delay for receiving fund from KIIFB, RBDCK requ