Kanakkuമലയാളം

Total of works

₹59.79 crore

₹59,79,00,437

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Aban junction Over Bridge

Scheduled completion was 30-04-2026. That was 155 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Aban junction Over Bridge

In progress
55%Physical progress
51.1%Financial progress
Scheduled start14-03-2022
Scheduled completion30-04-2026
Contractor
Sivasamy
Implementing agency (SPV)
KRFB
Contract amount
₹45,04,21,272₹45.04 crore
Amount paid
₹22,99,63,879₹23 crore
Paid to contractor
₹21,71,87,206₹21.72 crore
Administrative sanction (AS)
₹50,00,00,000₹50 crore
Financial sanction (FS)
₹59,79,00,437₹59.79 crore
Technical sanction (TS)
₹46,80,37,900₹46.8 crore
Tender amount
₹45,04,21,272₹45.04 crore
Letter of acceptance (LOA)
₹40,21,61,850₹40.22 crore
Current progress
Work ongoing. Land acquisition process started and 6(1) notification published. Installing alignment stone started, but not able to continue due to public protest. Hon. Minister and District Collector has agreed to conduct a meeting on 09/07/2022 with la

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹59,79,00,437₹59.79 crore

Details

Project code
PWD016-19-01
Department
Public Works
Constituency
Aranmula

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…