Aban junction Over Bridge
In progress55%Physical progress
51.1%Financial progress
Scheduled start14-03-2022
Scheduled completion30-04-2026
- Contractor
- Sivasamy
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹45,04,21,272₹45.04 crore
- Amount paid
- ₹22,99,63,879₹23 crore
- Paid to contractor
- ₹21,71,87,206₹21.72 crore
- Administrative sanction (AS)
- ₹50,00,00,000₹50 crore
- Financial sanction (FS)
- ₹59,79,00,437₹59.79 crore
- Technical sanction (TS)
- ₹46,80,37,900₹46.8 crore
- Tender amount
- ₹45,04,21,272₹45.04 crore
- Letter of acceptance (LOA)
- ₹40,21,61,850₹40.22 crore
- Current progress
- Work ongoing. Land acquisition process started and 6(1) notification published. Installing alignment stone started, but not able to continue due to public protest. Hon. Minister and District Collector has agreed to conduct a meeting on 09/07/2022 with la