Total of works

₹19.33 crore

₹19,32,89,118

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Kaduthuruthy ROB

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
RBDCK
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹30,00,00,000₹30 crore
Financial sanction (FS)
₹19,32,89,118₹19.33 crore
Current progress
LA requisition submitted to District Collector on 18.11.2019. LAO appointed as the Special Tahsildar LA KIIFB Kottayam. LA to be taken up after getting approval of GAD from railways. Final GAD submitted to Railways on 01.10.2021. Reminder letter submitte

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹19,32,89,118₹19.33 crore

Details

Project code
PWD016-22
Department
Public Works
Constituency
Kaduthuruthy

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Kaduthuruthy ROB
  • Scheduled start and completion dates · Kaduthuruthy ROB
  • Amount paid · Kaduthuruthy ROB