Flyover at Railway junction, Changanassery
Approved0%Physical progress
Not publishedFinancial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹90,00,00,000₹90 crore
- Financial sanction (FS)
- ₹62,11,00,000₹62.11 crore
- Technical sanction (TS)
- ₹72,96,45,445₹72.96 crore
- Tender amount
- ₹72,62,37,911₹72.62 crore
- Letter of acceptance (LOA)
- ₹61,54,55,857₹61.55 crore
- Current progress
- LA Requisition submitted on 19.06.2020. Administrative sanction from Revenue (B) Department received as per GO (Rt) No. 2402/2020/RD dt. 21.07.2020. Special Tahsildar LA KIIFB Kottayam has been appointed as LAO by DC on 13.08.2020. Boundary Stone planti