Pattambi Bridge
In progress8.3%Physical progress
7.6%Financial progress
Scheduled start24-03-2025
Scheduled completion24-03-2027
- Contractor
- M/s Arsjasminconstructionsprivatelimited
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹39,11,14,854₹39.11 crore
- Amount paid
- ₹2,96,89,061₹2.97 crore
- Paid to contractor
- ₹2,78,02,039₹2.78 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹52,58,59,404₹52.59 crore
- Technical sanction (TS)
- ₹52,57,60,000₹52.58 crore
- Tender amount
- ₹39,11,14,854₹39.11 crore
- Current progress
- FS Obtained including LA. It is mentioned in DAR that all LA procedures must be completed before sanction of TS. Agt executed for laying boundary/ alignment stone starting LA procedures. Work started. Request given to Govt. for Revenue A.S on19/7/2022