Total of works

₹14.02 crore

₹14,02,09,001

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Mannarkundu Bridge

Scheduled completion was 07-05-2026. That was 148 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Mannarkundu Bridge

In progress
9.5%Physical progress
3.2%Financial progress
Scheduled start08-02-2024
Scheduled completion07-05-2026
Implementing agency (SPV)
KRFB
Contract amount
₹14,41,27,038₹14.41 crore
Amount paid
₹46,55,847₹46.56 lakh
Paid to contractor
₹43,59,918₹43.6 lakh
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹14,02,09,001₹14.02 crore
Technical sanction (TS)
₹13,99,29,000₹13.99 crore
Tender amount
₹14,41,27,038₹14.41 crore
Current progress
FS obtained. TS estimate submitted and placed before the TS committee on 29.04.2022

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹14,02,09,001₹14.02 crore

Details

Project code
PWD016-44-01
Department
Public Works
Constituency
Kalpetta

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…