Mannarkundu Bridge
In progress9.5%Physical progress
3.2%Financial progress
Scheduled start08-02-2024
Scheduled completion07-05-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹14,41,27,038₹14.41 crore
- Amount paid
- ₹46,55,847₹46.56 lakh
- Paid to contractor
- ₹43,59,918₹43.6 lakh
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹14,02,09,001₹14.02 crore
- Technical sanction (TS)
- ₹13,99,29,000₹13.99 crore
- Tender amount
- ₹14,41,27,038₹14.41 crore
- Current progress
- FS obtained. TS estimate submitted and placed before the TS committee on 29.04.2022