CHOTTA BRIDGE
In progress87.2%Physical progress
73.8%Financial progress
Scheduled start11-01-2023
Scheduled completion31-12-2025
- Contractor
- T. A. Abdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,84,83,435₹19.85 crore
- Amount paid
- ₹14,64,00,577₹14.64 crore
- Paid to contractor
- ₹13,83,36,118₹13.83 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹19,95,84,858₹19.96 crore
- Technical sanction (TS)
- ₹19,88,84,858₹19.89 crore
- Tender amount
- ₹16,94,47,567₹16.94 crore
- Current progress
- FS obtained for an amount of Rs.18.30 Crores.TS Estimate Placed in TS Committee dated 24.05.2022.Corrections are incorpoarting in the TS estimate as per the suggestions of TS committe and submitted for approval.