This package
Work awarded₹11.89 crorepaid
₹11.89 croreapproved
₹11.05 crore
₹11,04,52,748
KIIFB status: WBS Base One Approved · How we group
On KIIFB's project status page this belongs to “Wayanad District Stadium”. The figures below are for that whole project, not this package alone.
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: