TSM002-01-06 Alappuzha

Revival of Saukar and Maqua Masjid, Alappuzha - Electrical Works

Spent on this package so far

₹3.84 lakh

₹3,83,900

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹17,19,08,196Estimate of sub-project TSM002-01, shared by 8 contract packages
Expenditure reported · this package
₹3,83,900
Expenditure reported · all 8 packages
₹2,78,47,59616.2% of the estimated amount

Details

Project code
TSM002-01-06
Department
Tourism
Executing agency
INKEL Limited
Constituency
AlappuzhaMLA: Shri P.P. Chitharanjan

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Alappuzha Heritage Project - Phase 1”. The figures below are for that whole project, not this package alone.

Approved
₹17,19,08,196₹17.19 crore
Paid so far
₹2,88,87,12516.8% of the amount approved

This package

Work awarded
₹4 lakhpaid
₹4 lakhapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project