TSM002-03-05 Alappuzha

Interior works for Museum of Labour Movement at New Model Coir Society

Spent on this package so far

₹33.12 lakh

₹33,11,609

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹13,38,78,097Estimate of sub-project TSM002-03, shared by 6 contract packages
Expenditure reported · this package
₹33,11,609
Expenditure reported · all 6 packages
₹3,91,31,69829.2% of the estimated amount

Details

Project code
TSM002-03-05
Department
Tourism
Executing agency
INKEL Limited
Constituency
AlappuzhaMLA: Shri P.P. Chitharanjan

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Alappuzha Heritage Project - Phase 3”. The figures below are for that whole project, not this package alone.

Approved
₹13,38,78,097₹13.39 crore
Paid so far
₹4,07,69,43830.5% of the amount approved

This package

Work started
₹34.28 lakhpaid
₹79.36 lakhapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress