Comprehensive WSS to Ponnani & adjoining Panchayaths - Package 2
Spent on this package so far
₹14.18 crore
₹14,17,69,924
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: WBS Base One Approved · How we group
Money trail
- Estimated amount
- ₹74,40,00,000Estimate of sub-project WRD002-06, shared by 3 contract packages
- Expenditure reported · this package
- ₹14,17,69,924
- Expenditure reported · all 3 packages
- ₹60,92,52,31281.9% of the estimated amount
Details
- Project code
- WRD002-06-02
- Department
- Water Resources
- Executing agency
- Kerala Water Authority (KWA)
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Comprehensive WSS to Ponnani & adjoining Panchayaths”. The figures below are for that whole project, not this package alone.
- Approved
- ₹74,40,00,000₹74.4 crore
- Paid so far
- ₹1,31,95,55,304₹131.96 crore
Source: KIIFB project status (kiifb.org). How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Comprehensive WSS to Ponnani & adjoining Panchayaths - Package 1 ₹38.29 crore spent
- WRD002 -06- 03 - KIIFB - CWSS to Ponnani Municipality and all Panchayath in Ponnani Taluk,Package - III - Raw water and Clear water Pump set,Transformer,Substation Building ,CW Pump set for existing UWSS to Ponnani & RWSS to Ponnani and Interlinking of existing CW Pumping main. ₹8.45 crore spent