WRD 002 09-AUGMENTATION OF UWSS TO KOTTAYAM MUNICIPALITY-Package II A- Laying, testing and commissioning 600 mm DI k9 CWPM from Existing Valvechamber @ Kwa Campus to Vedippura line, 600mm DI pipe from Manippuzha to Existing OHSR @ Mariyappally, Gap clossing Works and distribution system at various places...including Charging Etc.. Complete..-Pipeline Work
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Project Execution Document Stage 1 Approved · How we group
Money trail
- Estimated amount
- ₹50,00,00,000Estimate of sub-project WRD002-09, shared by 5 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 5 packages
- ₹31,66,15,20963.3% of the estimated amount
Details
- Project code
- WRD002-09-10
- Department
- Water Resources
- Executing agency
- Kerala Water Authority (KWA)
- Constituency
- KottayamMLA: Shri Thiruvanchoor Radhakrishnan
- Name as KIIFB publishes it
- KIIFB-KIIFB-WRD 002 09-AUGMENTATION OF UWSS TO KOTTAYAM MUNICIPALITY-Package II A- Laying, testing and commissioning 600 mm DI k9 CWPM from Existing Valvechamber @ Kwa Campus to Vedippura line, 600mm DI pipe from Manippuzha to Existing OHSR @ Mariyappally, Gap clossing Works and distribution system at various places...including Charging Etc.. Complete..-Pipeline Work
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Augumentation of Uwss to Kottayam Muncipality - Design, Construction and Commissioning of 50 MLD Output Capacity Conventional Type Water Treatment Plant and Allied Works at Perroor - Package I ₹18.74 crore spent
- Augmentation of UWSS to Kottayam Municipality - Package II - Supplying, Laying, Jointing, Testing, and commissioning of various HDPE pipes and distribution system at various places and Supply and erection of Clear Water Pump sets at KWA campus Pump House ₹12.16 crore spent
- 2016-17-WRD 002-09- Augmentation of WSS to Kottayam Municipality, Package II-Restoration of road damaged by laying pipelines along PWD Roads in Kottayam Municipal PWD Roads Division, Kottayam ₹76.09 lakh spent
- . Not published