WRD010-06-01 Chittur

Extension of Moolathara Right Bank Canal from Korayar to Varattayar

Spent on this package so far

₹149.9 crore

₹1,49,89,78,028

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · #1

Scheduled completion was 30-09-2025. That was 367 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Work 1

In progress
73.2%Physical progress
72.5%Financial progress
Scheduled start01-01-2022
Scheduled completion30-09-2025
Contractor
Kkconstructions
Implementing agency (SPV)
KIIDC
Contract amount
₹2,05,73,24,100₹205.73 crore
Amount paid
₹1,49,12,65,598₹149.13 crore
Paid to contractor
₹1,39,43,02,327₹139.43 crore
Administrative sanction (AS)
₹2,62,10,00,000₹262.1 crore
Financial sanction (FS)
₹2,55,18,26,030₹255.18 crore
Technical sanction (TS)
₹2,55,18,00,000₹255.18 crore
Tender amount
₹2,05,73,24,100₹205.73 crore

Money trail

Estimated amount
₹2,55,18,26,030Estimate of sub-project WRD010-06, shared by 3 contract packages
Expenditure reported · this package
₹1,49,89,78,028
Expenditure reported · all 3 packages
₹1,49,89,78,02858.7% of the estimated amount

Details

Project code
WRD010-06-01
Department
Water Resources
Constituency
ChitturMLA: Shri K. Krishnankutty

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Extension of Moolathara Right Bank Canal from Korayar to Varattayar”. The figures below are for that whole project, not this package alone.

Approved
₹2,55,18,26,030₹255.18 crore
Paid so far
₹1,66,22,05,41565.1% of the amount approved

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…