WRD022-09-01 Chittur

Construction of Regulator cum Bridge

Total of works

₹21.4 crore

₹21,40,47,641

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

RCB at Vadakarappally

Completed
100%Physical progress
95.1%Financial progress
Scheduled start12-01-2021
Scheduled completion15-01-2025
Implementing agency (SPV)
KIIDC
Contract amount
₹21,21,18,406₹21.21 crore
Amount paid
₹20,16,95,594₹20.17 crore
Paid to contractor
₹18,87,20,877₹18.87 crore
Administrative sanction (AS)
₹39,70,00,000₹39.7 crore
Financial sanction (FS)
₹21,40,47,641₹21.4 crore
Technical sanction (TS)
₹19,84,00,000₹19.84 crore
Tender amount
₹21,23,18,001₹21.23 crore
Letter of acceptance (LOA)
₹18,95,69,644₹18.96 crore
Current progress
10 span completed including abutment. 8 Sill beams erected. Retaining wall RB u/s 140m completed.LB 48m completed Retaining wall d/s 20m completed.LB 20m completed. Mechanical works: Fabrication of shutter works completed. Fabrication of hoisting

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹21,40,47,641₹21.4 crore

Details

Project code
WRD022-09-01
Department
Water Resources
Constituency
Chittur

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026