RCB at Vadakarappally
Completed100%Physical progress
95.1%Financial progress
Scheduled start12-01-2021
Scheduled completion15-01-2025
- Contractor
- M/S. Poonamgrahnirmanpvtltd
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹21,21,18,406₹21.21 crore
- Amount paid
- ₹20,16,95,594₹20.17 crore
- Paid to contractor
- ₹18,87,20,877₹18.87 crore
- Administrative sanction (AS)
- ₹39,70,00,000₹39.7 crore
- Financial sanction (FS)
- ₹21,40,47,641₹21.4 crore
- Technical sanction (TS)
- ₹19,84,00,000₹19.84 crore
- Tender amount
- ₹21,23,18,001₹21.23 crore
- Letter of acceptance (LOA)
- ₹18,95,69,644₹18.96 crore
- Current progress
- 10 span completed including abutment. 8 Sill beams erected. Retaining wall RB u/s 140m completed.LB 48m completed Retaining wall d/s 20m completed.LB 20m completed. Mechanical works: Fabrication of shutter works completed. Fabrication of hoisting