WRD022-12-01 Pattambi

Construction of Regulator cum Bridge

Total of works

₹29.48 crore

₹29,48,45,612

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · RCB at Kaladikunnu

Scheduled completion was 06-07-2025. That was 453 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

RCB at Kaladikunnu

In progress
45%Physical progress
25.2%Financial progress
Scheduled start06-01-2024
Scheduled completion06-07-2025
Implementing agency (SPV)
KIIDC
Contract amount
₹29,55,21,962₹29.55 crore
Amount paid
₹7,43,99,841₹7.44 crore
Paid to contractor
₹6,96,71,038₹6.97 crore
Administrative sanction (AS)
₹25,50,00,000₹25.5 crore
Financial sanction (FS)
₹29,48,45,612₹29.48 crore
Technical sanction (TS)
₹29,18,21,075₹29.18 crore
Tender amount
₹29,55,21,962₹29.55 crore
Current progress
Sent to CMD for appraisal

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹29,48,45,612₹29.48 crore

Details

Project code
WRD022-12-01
Department
Water Resources
Constituency
Pattambi

What we don't know yet