RCB at Kaladikunnu
In progress45%Physical progress
25.2%Financial progress
Scheduled start06-01-2024
Scheduled completion06-07-2025
- Implementing agency (SPV)
- KIIDC
- Contract amount
- ₹29,55,21,962₹29.55 crore
- Amount paid
- ₹7,43,99,841₹7.44 crore
- Paid to contractor
- ₹6,96,71,038₹6.97 crore
- Administrative sanction (AS)
- ₹25,50,00,000₹25.5 crore
- Financial sanction (FS)
- ₹29,48,45,612₹29.48 crore
- Technical sanction (TS)
- ₹29,18,21,075₹29.18 crore
- Tender amount
- ₹29,55,21,962₹29.55 crore
- Current progress
- Sent to CMD for appraisal